The drawing

M-101 Level 1 Mechanical Plan, Millbrook Branch LibraryARCH D sheet, 36 by 24 inches. Drawn at 1/8" = 1'-0". Use the layer tray and the measure tool below the drawing.ABCDE123VESTIBULE101LOBBY102CIRCULATION DESK103CHILDREN'S LIBRARY104COMMUNITY ROOM105CORRIDOR114STAIR 1112ELEVATOR113TOILET108TOILET109ELECTRICAL111MECHANICAL110STAFF WORKROOM107STORAGE106RTU-1RTU-1 ON ROOF ABOVE, SEE SCHEDULEEF-134x1630x1424x1210x818x1212x820x1222x1210x836x1636x1610x8S-1 250 CFMS-2 450 CFMS-3 450 CFMS-4 350 CFMS-5 600 CFMS-6 600 CFMS-7 650 CFMS-8 650 CFMS-9 300 CFMS-10 300 CFMS-11 300 CFMR-1 2000 CFMR-2 1675 CFME-1 200 CFME-2 200 CFMTT-1TT-2TT-3N08'-0"16'-0"24'-0"32'-0"1/8" = 1'-0"1 LEVEL 1 MECHANICAL PLANSCREENED BACKGROUND IS A-101, FOR REFERENCE ONLYMECHANICAL LEGEND24x12Duct, width by height in inchesCeiling supply diffuser, tag and air quantityCeiling return or exhaust grilleTThermostat, 48 in above the finish floorPackaged unit or fan, tagged to the scheduleAir quantities are in cubic feet per minute. A duct sizeis written as clear inside width by clear inside height,so 24x12 is 24 in wide and 12 in deep.MECHANICAL GENERAL NOTES01. Coordinate every duct run with the structure on S-201 and with thelighting on E-101 before fabricating. Ducts run below the joists unlessa section shows otherwise.02. Duct sizes shown are clear inside dimensions. Add the thickness of anyinternal lining to the sheet metal size.03. Balance the system to the air quantity shown at each terminal, withinten percent, and submit a balance report.04. Support the rooftop unit on the manufacturer's curb. Flash and counterflash the curb into the roofing.05. Provide a volume damper in the branch at every diffuser and grille,reachable through the ceiling.06. The exhaust fan runs whenever the toilet room lights are on. See thecircuit on E-101.07. Seal every duct joint. Duct work in an unconditioned space carries twoinches of exterior wrap.MECHANICAL EQUIPMENT SCHEDULETAGRTU-1EF-1DESCRIPTIONPackaged rooftop unit, gas heat and electric coolingCeiling exhaust fan, toilet roomsCFM4900400OA CFM1225-TONS12-MBH200-ELECTRICAL208 volt, three phase, 44 MCA, 60 amp maximum fuse120 volt, single phase, 1.4 ampRTU-1 operating weight 1450 lb. Location: roof above mechanical 110.AIR TERMINAL SCHEDULETAGS-1S-2S-3S-4S-5S-6S-7S-8S-9S-10S-11R-1R-2E-1E-2ROOM101102102103104104105105114114107114114108109SERVICESupplySupplySupplySupplySupplySupplySupplySupplySupplySupplySupplyReturnReturnExhaustExhaustCFM25045045035060060065065030030030020001675200200NECK OR FACE8 in round10 in round10 in round10 in round12 in round12 in round12 in round12 in round8 in round8 in round8 in round24x24 face24x24 face8 in round8 in roundNorthgate Design StudioArchitecture and interiorsStructural and civil: Kestrel EngineeringPROJECTMillbrook Branch Library412 Kestrel Avenue, MillbrookMillbrook Public Library DistrictProject number 2026-114ISSUE2026-08-14 Issued for constructionSCALE1/8" = 1'-0"DRAWNKECHECKEDQAREVISIONSNODATEDESCRIPTIONSHEET TITLELevel 1 Mechanical PlanSHEET NUMBERM-101
100%

Turn on Measure, then click two points on the drawing.

Layers on M-101

Drag to pan, scroll or pinch to zoom, or use the buttons. With the drawing focused, the arrow keys pan, plus and minus zoom, and 0 fits the sheet. Every tag, marker and dimension is a focusable target: press Tab to walk them and Enter to select one.

9 questions in the bank draw on this sheet.

How to read this sheet

A mechanical plan is an architectural plan with the air system laid over it. The first thing to do is separate the two. Everything drawn faintly is the architectural background: the walls, the door openings, the grid and the room tags, copied from A-101 and screened back so it cannot be mistaken for mechanical work. It is there so you can say where a duct is, and nothing on it is the mechanical contractor's scope. If the background disagrees with A-101, A-101 wins.

Everything drawn at full weight is the mechanical work. Start at the equipment. RTU-1 is a packaged rooftop unit sitting on the roof above Mechanical 110, drawn dashed on this plan because it is above the level being shown. Its tag sends you to the equipment schedule at the bottom of the sheet, which gives the supply air quantity, the outside air quantity, the cooling tonnage, the heating output and the electrical characteristics. A tag on a plan and a row in a schedule are always the same piece of equipment; the plan says where, the schedule says what.

Follow the air from there. A duct is drawn as two parallel lines the true width of the duct, with the size written along it as width by height in inches. The riser leaves the roof unit, drops through the roof curb and lands in Corridor 114, where the trunk splits east and west. Each trunk gets smaller as it gives air away, and the sizes on this sheet step down accordingly: the riser is the biggest, the trunks are next, and the branches into each room are the smallest. If a size looks wrong for the air it carries, you have found either a mistake or a duct you have mis-traced.

Every branch ends at an air terminal. A square with a diagonal cross is a supply diffuser; a square with parallel bars is a return or exhaust grille. Each carries a tag and the air quantity in cubic feet per minute right on the plan, and the same tag appears in the air terminal schedule with its room and its neck size. Reading a diffuser is a three step move: find the symbol, read the tag and the CFM beside it, then confirm the tag in the schedule.

The thermostats are the last piece. Each one is a small circle with a T, mounted on a wall in the room it controls, and it is the reason a room's air quantity is what it is. The legend at the top left names every symbol used, and the general notes state the rules that are not drawn: coordinate with the structure, balance to the quantities shown, damper every branch, and seal the joints.